Special Needs

St. Elizabeth Centre, Much Hadham, Essex

Clients
Aldwyck Housing Association

Description
Construction of 2 identical single storey detached residential blocks of traditional construction providing permanent accommodation for 10 no. adult residents with epilepsy and learning difficulties together with associated drainage, services, external works and off-site mains installations

Duration of Work
52 Weeks
Completion September 2005

Contract Value
£2.3 Million

Form of Construction
Traditional New Build

Employers Agent
Wilby and Burnett

Form of Contract
JCT 98 WCD + Amendments

Key Facts

  • Completed early and to a very high standard Project was built whilst Centre remained fully operational - required full co-operation between the parties
  • High level of specification internally for end users with special needs requiring detailed co-ordination between both the design team & site
  • Successful completion resulted in Phase ii being negotiated and awarded under a full open book partnering arrangement