General Needs Housing

St Peters Hill, Caversham

Clients
Toynbee Housing Association

Description
The construction of 22 flats and 8 houses for rent and shared ownership together with ancillary works

Duration of Work
38 weeks
Completed July 2004

Contract Value
£1.5 Million

Form of Construction
Traditional New Build

Employers Agent
BPP Construction Consultants

Form of Contract
JCT 98 Design and Build

Key Facts

  • Mixed tenure
  • Traditional Construction
  • Special provision was made in design of car park to protect very old and large walnut tree including installation of porous hardstanding
  • HPL took over the project after the original contractor went into liquidation part way through the construction period. This meant validating all the previous work